Home build cost calculator

What will your house really cost?

Your builder's price per square foot is only part of it. Add land, fees and a cushion to get the real number.

By

sq ft
$/ sq ft
$

Put 0 if you already own the lot.

$

Plans, engineering, surveys, permits, loan fees.

Cushion for surprises

Most builders suggest 10 to 15% of the build.

All in, about

$770,000

The builder's quote is $600,000. Land, fees and a 10% cushion add $170,000 on top.

  • House$600,000
  • Land$85,000
  • Fees$25,000
  • Cushion (10%)$60,000

Open “Check it against your loan and cash” to see whether your money covers it.

Groundbase turns this into a budget you can track as real bills come in.

Start free

Most home build budgets start with a builder's price per square foot. That number covers the house. It usually does not cover the land, the design and permit fees, or the cushion you need when something changes. This calculator adds those back, so the first number you plan around is an honest one.

Common buffer

10-15%

contingency on the construction cost

Often missed

8-12%

added by design, permits, engineering, and fees

The real check

Loan + cash

compared against the full project cost

What the estimate includes

  • Construction cost: home size times the quoted cost per square foot.
  • Land: enter 0 if you already own the lot.
  • Design, permits, and fees: plans, engineering, surveys, permits, and loan fees. These soft costs often add 8 to 12% on top of construction.
  • Contingency: a percentage of the construction cost. Land is a settled price and fees rarely move, so contingency is not applied to them.
  • Funding check: your construction loan plus available cash, compared with the total.

A worked example

Say your builder quotes $250 per square foot for a 2,400 sq ft house. That is $600,000 for the house itself. Now add what the quote leaves out:

  • Land: $85,000
  • Design, permits and fees: $25,000
  • A 10% cushion on the build: $60,000

The real total is $770,000, which is $170,000 more than the quote. With a $560,000 construction loan and $120,000 in cash, you have $680,000, so you would be $90,000 short before the first shovel goes in. Far better to find that out now than at the last draw.

What to add before you commit

A quick estimate is a starting point, not a budget. Before you sign with a builder or lock a loan amount, check for the costs that sit outside a per-square-foot quote. Site work is the big one: driveway, grading, septic or sewer, well or water, and utility connections can move the total a lot, especially on rural lots.

Construction loan interest is the other. During the build you usually pay interest on what has been drawn, and that cost grows as the project moves. The construction loan interest calculator estimates it from your loan size, rate, and build length.

From a first estimate to a budget you can track

Once the build is real, the estimate becomes a working construction budget: categories, allowances, a contingency line, and actual costs arriving every month. That is where Groundbase, a home building budget app for homeowners, picks up. It tracks actual costs and change orders against the budget and connects them to your funding, construction loan draws, interest, and finished mortgage payment.

Common questions

Does the price per square foot include land?

Usually not. A builder's per-square-foot price covers the house itself. Land, site work like the driveway and utility hookups, and design and permit fees are normally extra, which is why this calculator asks for them separately.

How much contingency should I add to a home build?

Most builders and lenders suggest 10 to 15% of the construction cost. Lean toward 15% or more if the site has unknowns, the design is complex, or prices in your area are moving fast.

What are soft costs when building a house?

Soft costs are the expenses that aren't part of the building itself: plans, engineering, surveys, permits, inspections and loan fees. They often add 8 to 12% on top of construction and are easy to undercount.

Why doesn't the cushion apply to land and fees?

The land price is settled once you buy it, and fees rarely move much. Overruns happen in the construction itself, so the cushion is sized off the build.

Keep the full picture in one place.

Groundbase connects your budget, funding, draws, and finished-home payment so nothing gets lost between your lender and your spreadsheet.

7-day free trial. Cancel anytime.